Obviously too logical! However, our slab was poured and it didn't start raining until 4 or 5 hrs later....
I was surprised this morning when I got out there to find our frames being delivered! The builder had told me that they were made and as soon as he could get the slab on the ground things would get moving....so as soon as the slab is cured off we go!